Question

    A contractor hired 80 workers to complete a work in 60

    days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.
    A 95 Correct Answer Incorrect Answer
    B 50 Correct Answer Incorrect Answer
    C 20 Correct Answer Incorrect Answer
    D 80 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying, Therefore, 80 extra workers are needed so that work gets completed on time.

    Practice Next

    Relevant for Exams: