Question
"Amit" and "Bhanu" have respective completion times of
20 and 30 days for a task. They began working together on the project, but after a few days, "Amit" left and "Chintu," who can finish the entire task on her own in ten days, joined. Four days before the job was finished, "Chintu" left. Determine the amount of work completed by "Bhanu" if "Amit" and "Chintu" worked for a similar number of days.ÂSolution
ATQ, Let the total work = 60 units (L.C.M of 20, 30 and 10) Therefore, efficiency of ‘Amit’ = 60/20 = 3 units/day Efficiency of ‘Bhanu’ = 60/30 = 2 units/day Efficiency of ‘Chintu’ = 60/10 = 6 units/day Let ‘Amit’ and ‘Chintu’ worked for ‘d’ days According to the question, 5d + 8d + 4 × 2 = 60 13d = 52 Or, d = 4 Therefore, work will get completed in d + d + 4 = 12 days Therefore, work done by ‘Bhanu’ = 12 × 2 = 24 units Required ratio = 24/60 = 2/5
Which of the following teams had won the T 20 IPL match 2022 ?
What is the name of Chandrayaan 3's rover?
In which Schedule of the Constitution of India were 22 languages mentioned?
The Khalji Dynasty ruled over Delhi from ______.
Converting a large punishment to light sentence is called-
A light bulb working on a 18 V battery draws a current of 3 A. What will be the resistance of the bulb?
What is the intermediate level in the Panchayati Raj Institutions called?
In India, cricket was brought by whom?
What is the total fertilizer subsidy allocated by the government for the 2023-24 including urea and DAP subsidies?
The 42nd amendment of the Indian Constitution added ________.