Question
28 typists working 5 hours per day can complete a typing job in 18 days. ____ typists working _____ hours per day can complete (5/6)th part of the work in 15 days. The values given in which of the following options will fill the blanks in the same order in which it is given to make the statement true:
28 typists working 5 hours per day can complete a typing job in 18 days. ____ typists working _____ hours per day can complete (5/6)th part of the work in 15 days. The values given in which of the following options will fill the blanks in the same order in which it is given to make the statement true:
I. 32, 6
II. 40, 5
III. 25, 8
More Time and work Questions
- P does one fourth as much work as Q in two third of the time. If together they take 24 days to complete the work, how much time shall Q take to do it?
- There is enough food in a camp to last for 40 days if each of the 60 soldiers present at the camp eat 3 times a day. After 10 days, 10 soldiers left the ca...
- 28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more women...
- A can complete a piece of work in 12 days , and B can complete it in 18 days . They work together for 4 days , and then A leaves. In how many more days...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. They started working together but ‘A’ left after 4 days. Find the time taken by ‘B...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- ‘A’ alone can complete a piece of work in 30 days while ‘A’ and ‘B’ together can complete the same work in 20 days. ‘B’ started the work and after 4 days ‘...
- A team of 'x' boys can complete a job in 18 days if they all work together. However, every day, 15 boys leave the team after starting the task, and it now ...
- A, B, and C together can do a project in (64/7) days. B and C together need (96/9) days, and C alone completes half in 8 days. Find A : B (efficiency).
- Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 days,...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)