Question
Raman and Shyam can finish a task in 9 days working together. Shyam can finish that task alone in 12 days. How much time will Raman alone take to finish it?
More Time and work Questions
- ‘R’ and ‘S’ can together finish a job in 18 days. If ‘R’ alone can finish it in 30 days, how many days will ‘S’ alone take?
- 'A' alone can do some work in 20 days. 'B' is 60% more efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to ...
- A alone can complete a piece of work in 15 days, and B alone can complete it in 20 days. They work together, but every third day B does not work. In how ma...
- 'A' and 'B' alone can complete a work in 9 days and 18 days, respectively. Find the time taken by them to complete the work if they work on alternate days ...
- Komal and Seema individually can complete a task in ‘2a’ hours and ‘4a’ hours respectively. If they together can complete (3/4)th of the work in 2 hours, t...
- Three workers, A, B, and C, can complete a task in 40 days, 72 days, and 45 days respectively. They start working together, but A leaves 20 days before the...
- 'X' can complete 75% of a work in 15 days, whereas 'Y' can complete 25% of the same work in 10 days. They both started working together, but 'Y' left the j...
- There is enough food in a camp to last for 60 days if each of the 20 soldiers present at the camp eat 5 times a day. After 30 days, 10 more soldiers joined...
- A can do a job alone in 66 days, B can do it alone in 55 days, while A, B, and C working together can complete the job in 11 days. In how many days can C d...
- The efficiency of A is half than that of B and C together. The ratio of the efficiency of B and C is 5 : 4. A, B and C together can do this work in 12 days...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Efficiency of Ram =4-3=1 Total work Ram alone takes to finish=36/1 = 36 days.