Question
P, Q, and R can complete a work in 12 days. 15 days and
30 days, respectively, working alone. How soon can the work be completed if Q is assisted by P and R on alternate days?Solution
Total work = 60 (LCM of 12, 15 and 30) P's efficiency = 60/12 = 5 Q's efficiency = 60/15 = 4 R's efficiency = 60/30 = 2 Pattern of work = PQ, QR, PQ, QR... Work done by PQ and PR in 2 days = (5 + 4) + (4 + 2) = 15 2 days = 15 units 2 Γ 4 = 8 days => 15 Γ 4 = 60 units In 8days complete total work.
In advertising, Frequency is defined as the:
In planning and obtaining publicity, a frequently used tool is the:
Quick response and efficient consumer response delivery systems are most closely related to:
The likely final outcome of poor segmentation is?
According to one of the world's largest publishers, it was unprepared for recent increases in the demand for books about security. To prepare for the sh...
The means by which the advertising message is communicated to the target audience is through:
When a businessman issues many ads in different langages and distributes in different areas he is recognizing the importance of:
A marketing strategy is the means by which a marketing goal is to be achieved. Two factors that usually characterizing a marketing strategy are:
In physical distribution decisions, total logistics cost includes each of the following EXCEPT:
In a situation where coffee bean prices doubled, resulting in the price of coffee doubling as well, consumers may switch to tea, where the prices remain...