Question
40 men take 15 days to finish some work. If the work is
to be finished in 8 days, then how many additional men should be hired?Solution
Let the total work be 'w' units and efficiency of each man be 'e' units/day Let number of men required to finish the work in 8 days be 'm'. ATQ; W/(40 x 15 x e) =Â W/(8 x e x m) Â m = 75 So, 75 - 40 = 35 more men should be hired.
12 children and 18 men complete an artwork in 9 days. Each child takes twice as long as a man to finish the artwork. How many days will it take for 18 m...
'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency w...
A can complete a task 40% more efficiently in 25 days, whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at...
- If a group of 15 boys and 10 girls can finish a task in 36 days, and a team of 5 girls alone can complete the same task in 72 days, how long will it take f...
‘A’ is 40% more efficient than ‘B’. ‘A’ and ‘B’ work together for 8 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C�...
Alice can build one section of a wooden fence with a base length of 18 meter and a height of 25 meter in 18 days. Bob can construct 80% of one side of a...
'Preeti' can complete a piece of work in 70 days, while 'Bhanumati' can complete it in 90 days. They both started the work together, but 'Preeti' left a...
A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves....
Pooja can complete a task in 45 days and Kavita in 30 days. A third person, Mehul, is 20% more efficient than both of them combined. How many days will ...
P can do a piece of work in 15 days, Q can complete double the work in 30 days and R can do the work in 25 days. If all of them together earn Rs. 2600, ...