Question
'Arun' alone can complete 60% of the work in 15 days,
while 'Arun' and 'Bhaskar' together can complete 80% of the work in 7.5 days. Find the time taken by 'Bhaskar' alone to finish the work.Solution
Time taken by 'Arun' alone to complete the work = (15/0.6) = 25 days Time taken by 'Arun' and 'Bhaskar' together to finish the work = (7.5/0.80) = (75/8) days Let, the total work be LCM of [25 and 75] = 75 units So, the efficiency of 'Arun' = (75/25) = 3 units/day Sum of efficiencies of 'Arun' and 'Bhaskar' together = [75/(75/8) ] = 8 units/day So, the efficiency 'Bhaskar' = 8 - 3 = 5 units/day Time taken by 'Bhaskar' alone to finish the work = (75/5) = 15 days
To which race did Mahmud of Ghazni belong?
Consider the following statements with reference to the Sikh ruler Ranjit Singh:
1. He was the chief of the Sukerchakia misl.
2. He moder...
Consider the following statements
1. The civil disobedience movement was the widespread participation of Women.
2. The formation of t...
When was the All India Muslim League established during the era of British rule in India?Â
The Two Nations theory was propounded by Jinnah in :
With reference to the Civil Disobedience movement and the Swadeshi Movement, consider the following statements
1. Both the movements were a direc...
Which ruler of the Mauryan Empire constructed the Sanchi Stupa?
Which of the above statements is/are correct?
With reference to Awadh, Consider the following statements:
1. Saadat Khan was appointed as the governor of Awadh by Mughal Emperor Ahmad Shah....
The system of "Communal Electorate" was first introduced in India by which British Act?