Question

    8 men working 6 hours a day can complete a piece of work

    in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women working 4 hours a day are needed to complete the work in 12 days?
    A 4 Correct Answer Incorrect Answer
    B 5 Correct Answer Incorrect Answer
    C 8 Correct Answer Incorrect Answer
    D 6 Correct Answer Incorrect Answer

    Solution

    Let the efficiency of each man be 'M' units/day. Let number of women required to complete the work in 12 days be 'N'. So, efficiency of each woman = '1.2M' units/day ATQ: We have, 8 X M X 6 X 6 = N X 1.2M X 4 X 12 Or, 288 = N X 57.6 So, 'N' = (288/57.6) = 5

    Practice Next

    Relevant for Exams: