Question

    If A can complete a job in 15 days and B can complete

    the same job in 10 days, and they work together for 4 days before A leaves. How many more days will B take to finish the job alone?
    A 3.33 days Correct Answer Incorrect Answer
    B 6 days Correct Answer Incorrect Answer
    C 7.5 days Correct Answer Incorrect Answer
    D 5 days Correct Answer Incorrect Answer

    Solution

    A's work rate = 1/15; B's work rate = 1/10. Combined work rate = 1/15 + 1/10 = (2 + 3) / 30 = 5/30 = 1/6. Work done in 4 days = 4 * (1/6) = 2/3. Remaining work = 1 - 2/3 = 1/3. B's time to finish remaining work = (1/3) / (1/10) = (1/3) * 10 = 10/3 = 3.33 days.