A can complete a certain work in 12 days, while B can complete it in 15 days. After working together for 4 days, A leaves and B continues working alone. How many additional days will B take to finish the remaining work?
A's work rate = 1/12, B's work rate = 1/15 Combined work rate = 1/12 + 1/15 = (5 + 4) / 60 = 9/60 = 3/20 Work done in 4 days = 4 * (3/20) = 12/20 = 3/5 Remaining work = 1 - 3/5 = 2/5 B's work rate = 1/15, so time taken by B = (2/5) / (1/15) = (2/5) * 15 = 6 days
A sheet of paper has been folded as shown by the question figure. You have to figure out from amongst the four answer figures how it will...
Question image:
Identify the answer figure from which the pieces given in question figure have been cut.
How many triangles are there in the diagram below:
Select the answer figure which is the same as question figure
Which answer figure will complete the pattern in the question figure?
Choose which of the following figures completes the pattern. Question Image: Which answer figure completes the form in the question figure?