Question

    'A' can complete a project in 15 days but worked only

    the first 4 days. 'B', who is 80% as efficient as 'A', takes over. How long does 'B' need to finish the remaining work?
    A 11(3/4) days Correct Answer Incorrect Answer
    B 13(3/4) days Correct Answer Incorrect Answer
    C 13(1/4) days Correct Answer Incorrect Answer
    D 11(1/4) days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'A' be 'x' units/day So, efficiency of 'B' = '0.8x' units/day Total work = x X 15 = '15x' units Work done by 'A' in 4 days = 4 X x = '4x' units So, remaining work = 15x - 4x = '11x' units So, time taken by 'B' to finish the remaining work = (11x ÷ 0.8x) = 13(3/4) days

    Practice Next

    Relevant for Exams: