‘P’ can complete 40% of a task in 24 days, while ‘Q’ can complete 25% of the task in 20 days. How long will it take approximately for ‘P’ and ‘Q’ together to finish 75% of the entire work?
More Time and work Questions
- 16 men can complete a work in 10 days. 10 men started the same work and left after working for ‘y’ days. The remaining work is completed by 6 men in 15 day...
- 40 men can complete a piece of work in 48 days. ‘x’ men started the work and after 30 days 56 more men joined them so that whole work was finished in the d...
- ‘C’ and ‘D’ can complete a piece of work together in 24 days. If ‘C’ alone can complete it in 40 days, how long would ‘D’ take to do the same work alone?
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- 168 unit of work can be completed by P alone in 28 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- Ashish and Anil can do a piece of work in 12 days and 16 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the r...
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
- Ajay alone can finish 60% of a task in 18 days. Vijay takes 15 days longer than Ajay to complete the entire task. When Vijay and Chirag work together, they...
- Ravi and Sita together can complete a piece of work in 150 days and 3 minutes, while Sita and Ramesh together can complete the same work in 90 days and 2.5...
- A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the wor...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)