Question
'P' and 'Q' can finish a piece of
work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' days, ensuring that the entire work is completed in '2r' days. Find the value of 'r'.Solution
ATQ,
Let the total work be 90 units. {LCM of 45 and 90} Efficiency of 'E' = 90 Ă· 45 = 2 units/day Efficiency of 'F' = 90Ă· 90 = 1 units/day So, 2r + 2r + 1r = 90 Or, 5r = 90 Therefore, r = 18
Special Drawing Rights (SDR) is an international reserve asset, created by the IMF in which of the following years?
Who was named Director of the Prime Minister’s Museum & Library in the June 2025?
As per Union Budget 2025-26, what is the total outlay proposed for the Nuclear Energy Mission aimed at Small Modular Reactors (SMRs)?
State which of the following statements is not correct about the dance of Lavani.
i. A combination of traditional song and da...
In MUDRA Bank, what does MUDRA stands for -
In which of the following year RBI introduced Account Aggregator Framework
International Birds Festival is to be held in Dudhwa National Park. It is in the state of:
The Limit for Foreign Portfolio Investments under Voluntary Retention Route (VRR) is set to be enhanced to how much from 01.04.2022 by RBI:
Which of the following is not a regulator of financial sector
Which of the following is a feature of the Women Entrepreneurship Program launched by NSDC?