Question
If one child has half the work efficiency of an adult,
determine the duration required for 8 children to construct a wall, which is 60% as large as the one built by 12 adults in 15 days.Solution
Let the efficiency of each man be '2x' units/day So, total work = 2x X 12 X 15 = '360x' units And efficiency of a child = 2x ÷ 2 = 'x' units/day So, required time = (360x X 0.6) ÷ (8 X x) = 27 days Hence, option a.
Zia wants to increase total revenue at his restaurant. The price elasticity of demand for several dishes that he serves are given in the table...
Money multiplier equals:
Which of the following is true about Omission(Overfitted) and Inclusion(Underfitted) type of the specification error
A "hedge fund" is typically characterized by:
As per recent economic survey, what role did the RBI's monetary policy play in controlling core inflation in FY24?
The "Balanced Budget Multiplier" states that if the government increases expenditure and taxes by the same amount, the net effect on national income is:
What is the Capital to RiskWeighted Assets Ratio (CRAR) of scheduled commercial banks (SCBs) as of end March 2024 according to the Financial Stability R...
The optimal quantity of the Public good to be produced is given by
Find MR when ed=0.5 and P=10