Let total amount of work = 288 units (LCM of 32 and 36) Amount of work done by A in one day = 288/32 = 9 units Amount of work done by B in one day = 288/36 = 8 units Amount of work done by A and B together in 12 days = 12 × 17 = 204 units Remaining work = 288 – 204 = 84 units Desired time = 84/8 = 10.5 days Hence, option c.