Question
A red JCB machine can complete the excavation of a field
in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines operate simultaneously for 4 days, what fraction of the field will they have excavated together?Solution
Let total work = 150 units Amount of work done by Red JCB machine in one day = 150/10 = 15 units Amount of work done by Green JCB machine in one day = 150/15 = 10 units Amount of work done by both machine in one day = 15 + 10 = 25 units Time taken by both machines together to complete the work = 150/25 = 6 days So the part of work done by both the machines together in 4 days = 4/6 = 2/3 Hence, option d.
What is used to make computer chips?
Which of the following is used for data exchange between devices in a local area network (LAN)?
___is the shortcut key to delete cells, rows or columns in the microsoft excel.
Documents converted to .......... can be published to the Web.
In associative mapping, in a 16 bit system the tag field has ______ bits.
Which of the following is used in main memory?
_______ translates the semantic instructions developed by programmers into machine language.
Which of the following is a type of malware intentionally inserted into a software system that will set off a malicious function when specified conditio...
In Windows, which of the following is the shortcut to lock your computer?
Which one of the following is used to combine two or more cell and formatting one big cell?Â