A red JCB machine can complete the excavation of a field in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines operate simultaneously for 4 days, what fraction of the field will they have excavated together?
Let total work = 150 units Amount of work done by Red JCB machine in one day = 150/10 = 15 units Amount of work done by Green JCB machine in one day = 150/15 = 10 units Amount of work done by both machine in one day = 15 + 10 = 25 units Time taken by both machines together to complete the work = 150/25 = 6 days So the part of work done by both the machines together in 4 days = 4/6 = 2/3 Hence, option d.
When is International Customs Day observed annually?
The Government of India has launched the residential education scheme 'Shreshtha' for which category of students?
Consider the following statements regarding the Republic of Dagestan:
1. It is located within the China
2. It shares boundary with the...
Who was elected as Iceland's President in 2024, becoming the second woman to hold this position?
Which company is going to launch earthquake warning service in India?
How many Vande Bharat trains was recently flagged off by Prime Minister Narendra Modi?
Who has been appointed as managing director and chief executive officer of South Indian Bank?
Which of the following countries have become a full time member of SCO (Shanghai Cooperation Organization)?
In which sector is the ULLAS initiative primarily focused, as part of the government's efforts to promote financial inclusion and literacy among underse...
Bandhavgarh National Park, famous for its Royal Bengal Tigers, is located in which Indian state?