    Individuals 'A', 'B', and 'C' can complete a certain task independently in 3, 4, and 6 days respectively. If they collaborate on the task, how many days will it take them to finish it together?

    A 2 days Correct Answer Incorrect Answer
    B 3/2 days Correct Answer Incorrect Answer
    C 4/3 days Correct Answer Incorrect Answer
    D 1 day Correct Answer Incorrect Answer

    Solution

    Let the total work be {LCM of 3, 4, and 6} 12 units Efficiency of 'A' = (12/3) = 4 units/day Efficiency of 'B' = (12/4) = 3 units/day Efficiency of 'C' = (12/6) = 2 units/day Sum of the efficiency's 'A', 'B', and 'C' = (4 + 3 + 2) = 9 units/day Required time taken = (12/9) = (4/3) days