Question
A, B, and C can finish a work in 12, 15, and 20 days,
respectively. They all start working together, but A leaves after 4 days, and B leaves after 1 more days. How much longer will C take to finish the remaining work?Solution
Work done by A in 4 days = 4 / 12 = 1/3. Work done by B in 5 days = 5 / 15 = 1/3. Total work done by A and B = 1/3 + 1/3 = 2/3. Remaining work = 1 - 2/3 = 1/3. Work done by C per day = 1/20. Time taken by C to finish 1/3 work = (1/3) / (1/20) = 20 / 3 = 6.67 days But since 5 days he was working with them, which means he will take extra = 6.67 – 5 = 1.67 days Correct answer: a) 1.67 days.
A Public company should hold at least ______ meetings in a year.
Which of the following are part of Market Infrastructure institutions?
An effective MIS (Management Information System) should have all the features, except?
In relation to the CGTMSE scheme, w hich of the following is correct with respect to the a security being considered as the primary security?  Â
...Consider the following about financial market instruments:
1. Commercial Papers are unsecured, short-term instruments issued by corporations to m...
An insurance company wants to estimate the average claim amount for motor insurance policies. They take multiple random samples of 50 claims each from ...
According to the IRAC Norms, a loan where the borrower has defaulted on payment for over 12 months is classified as _________
What is the threshold f or mandatory onboarding in TReDS for buyers?
According to Section 6 of the Indian Trusts Act, 1882, a trust becomes void if its purpose becomes unlawful after its creation due to changes in the law...
Which ethical principle involves treating others with fairness and impartiality?