Question
Thirty men working 8 hours daily
complete a task in 16 days. If the work increases to three times the original and needs to be finished in 20 days by workers putting in 6 hours per day with a 20% increase in their efficiency, how many men are required?Solution
ATQ, Let the total work be 'W' units and eiciency of each man be 'E' units/hour Let the number of men required be 'M'. ATQ: {(30 X 16 X 8 X E)/W} = {(M X 20 X 1.2E X 6)/(3 X W)} Or, M = 80
Which of the following is an essential element under Section 74 (Assault or criminal force to outrage modesty)?
Who is considered the father of Analytical Jurisprudence, emphasizing law as a system of rules separated from morality?Â
Admissions are:
According to Section 2(28)(h), which duty qualifies an officer as a public servant?Â
Sapinda Relationship is based on the principles of:
The Indian Succession Act, 1925, applies to:
Consider the following statements regarding the definition of "Public Servant" under the Prevention of Corruption Act, 1988:
Statement 1: A publi...
Consider the following statements regarding amendments to PMLA in 2012:
Statement 1: The 2012 amendments expanded scheduled offences to include c...
Pleadings are:
Who is the executive head of the State?