ATQ, Let the total work be 'W' units and eiciency of each man be 'E' units/hour Let the number of men required be 'M'. ATQ: {(30 X 16 X 8 X E)/W} = {(M X 20 X 1.2E X 6)/(3 X W)} Or, M = 80
Ratio of the work done by P, Q and R in one day is 7:4:9 respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 d...
Fifteen workers need 20 days to produce 2000 centre fresh. Now, if the goal is to manufacture 4000 center fresh within 25 days, how many workers are nee...
‘A’ alone can complete a work in 15 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 5 days, then...
Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 da...
A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job...
X can do a piece of work in 36 days. He worked at it for 6 days and then Y finished it in 20 days. In how many days can X and Y together finish the work...
‘X’ and ‘Y’ together can complete a work in 16 days, while ‘Y’ and ‘Z’ together can complete the work in 10 days. If ‘Y’ takes 20 da...
The time taken by ‘A’ to build a wall alone is 50% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percen...
'N,' 'V,' and 'R' have individual work completion times of 140 days, 112 days, and 80 days, respectively. They all started working together on a task, b...
‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...