ATQ, Let total task = 30 units {LCM of 10 and 15} Efficiency of 'Amit' = 3 units per day Efficiency of 'Bheem' = 2 units per day Since, they completed the whole task together therefore ratio of wage received by them will be same as the ratio of their efficiencies. So, required wage received by 'Amit' = {3/(3 + 2)} × 600 = Rs. 360