Question

    A company hires workers A, B, and C to finish a project.

    A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days. They start working together, but after 5 days, A leaves. How many more days will B and C together take to finish the remaining work?
    A 6 days Correct Answer Incorrect Answer
    B 7 days Correct Answer Incorrect Answer
    C 8 days Correct Answer Incorrect Answer
    D 4 days Correct Answer Incorrect Answer
    E 10 days Correct Answer Incorrect Answer

    Solution

    Work done by A, B, and C in 1 day = 1/30 + 1/24 + 1/20 = 4/120 + 5/120 + 6/120 = 15/120 = 1/8 of the project per day. Work completed by all in 5 days = 5 × 1/8 = 5/8 of the project. Remaining work = 1 - 5/8 = 3/8 of the project. Work done by B and C together in 1 day = 1/24 + 1/20 = 5/120 + 6/120 = 11/120 of the project per day. Time taken by B and C to finish the remaining 3/8 work = (3/8) ÷ (11/120) = 3/8 × 120/11 = 45/11 = 4.09 days.= 4 days(approx)

    Practice Next