Question
"A" and "B" together can complete a task in 16 days.
Additionally, "B" alone is able to complete 40% of the task in 16 days. Based on this information, calculate the time it would take for "A" to complete 60% of the task on their ownSolution
Time taken by 'B' to do 100% of the work alone = 16 Ć· 0.4 = 40 days Let total work be 80 units {LCM (40 and 16)} So, efficiency of 'B' = 80 Ć· 40 = 2 units/day And efficiency of 'A' and 'B' together = 80 Ć· 16 = 5 units/day So, efficiency of 'A' = 5 - 2 = 3 units/day So, required time = 80 X 0.6 Ć· 3 = 16 days
Which Indian state will host the World Audio Visual and Entertainment Summit (WAVES) in November 2024?
āGramin and Krishi Vikas Samitiā was established at which place?
With what metal is copper alloyed/mixed to form Constantan?
Which animal is represented by the mascot "Moga" for the 37th edition of the Indian National Games 2023?
Who inaugurated the first 'Global Symposium on Farmers' Rights' (GSFR) at the ICAR Convention Centre in New Delhi?
In which village of Chamoli district were megalithic burials discovered in 1956?
Who has launched āCall before u digā Application ?
a.Ā Ā Ā āCall Before uĀ Digā isĀ mobileĀ application .
b.Ā Ā Ā This is t...
āPatan Patola,ā a double ikat woven fabric scarf usually made from silk, was recently in the news. Which of the following region does this Geographi...
Under the newly approved Unified Pension Scheme (UPS), what percentage of a deceased employee's pension is received by their family?
Regarding the National Human Rights Commission (NHRC), consider the following statements:
1.The NHRC investigates complaints related to human rig...