Question

"A" and "B" together can complete a task in 16 days. Additionally, "B" alone is able to complete 40% of the task in 16 days. Based on this information, calculate the time it would take for "A" to complete 60% of the task on their own

A 12 days
B 16 days
C 20 days
D 21 days