Aman's work rate: 1/20 (since he finishes the work in 20 days). Bittu's work rate: 1/30 (since he finishes the work in 30 days). Chintu's work rate: 1/60 (since he finishes the work in 60 days).
Work done in a 3-day cycle: Days 1 and 2: Only Aman works, completing 1/10 of the work in 2 days. Day 3: Aman, Bittu, and Chintu work together, completing 1/10 of the work.
So, in each 3-day cycle, they complete 2/10 =1/5 of the work.
Total time = To complete the entire work, it will take 5 cycles (since = 1/(1/5) = 5
Each cycle takes 3 days, so the total time is 5×3 = 15 days.
It will take 15 days for the work to be completed.
How much additional financing did the World Bank approve to support India’s low carbon transition?
According to the April 2024 IFSCA Circular, which of the following types of trading is permitted for Remote Trading Participants (RTPs)?
If a stock's expected return is 18%, the risk-free rate is 6%, and the market return is 12%, what is the stock's beta according to the CAPM?
Which of the following country opens its first campus in GIFT City?
How many Free Trade Agreements (FTAs) did India sign between 2021 and 2024?
What is the minimum net worth required for a foreign entity interested to act as a clearing member in Bullion Exchange as per the notification provided ...
The economy of Country Z is in a recession, with declining GDP, rising unemployment, and low consumer and business confidence. The government is conside...
As per the recent guidelines by RBI for issuance of Share Capital by Rural Co-operative Banks, what is the limit of the outstanding amount of PNCPS and ...
Sales Rs. 50,000; Variable cost Rs. 30,000; Net profit Rs. 6,000; fixed cost is_____.
The entity willing to act as a Qualified Supplied-Limited Purpose Trading Member (QS-LPTM) on a Bullion Exchange shall be required to have net worth of...