Question
Ankit began a task but left it
after working for 32 days. The remaining 60% of the task was then completed by Bittu and Sittu working together over 45 days. Sittu is 120% more efficient than Bittu. Determine how long Sittu would take to complete 22% of the task on his own.Solution
ATQ, Total time taken by ‘Bittu’ and ‘Sittu’ to complete the whole task = 45/0.6 = 75 days Time taken by ‘Ankit’ to complete total task = 32/0.40 = 80 days Let total work = 1200 units (LCM of 75 and 80) Efficiency of ‘Ankit’ = 1200/80 = 15 units/day Efficiency of (Bittu + Sittu) = 1200/75 = 16 units/day Let the efficiency of ‘Bittu’ be ‘b’ units/day Efficiency of ‘Sittu’ = 2.20 × b = 2.2b units/day According to the question, 2.2b + b = 16 Or, 3.2b = 16 Or, b = 5 Therefore, efficiency of ‘Bittu’ = b = 5 units/day Efficiency of ‘Sittu’ = 16 – 5 = 11 units/day Time taken by ‘Sittu’ to complete 22% of the task = (0.22 × 1200)/11 = 24 days
- Two pipes, A and B, can fill a tank together in 72 minutes. Both pipes are turned on at the same time. However, pipe B is turned off after 60 minutes, and ...
The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will ...
Aman, Arun and Abraham can complete a work in 12, 20 and 24 days respectively. They all start working together. Aman left the work 1 day before its comp...
- 'P', 'Q', and 'R' can complete a job in 60, 90, and 120 days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leav...
A can finish a job in 30 hours while B can finish it in 20 hours. If C is (300/7)% more efficient than A and B together, then find the time taken by C a...
‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 10 hours. If ‘B’ completed the rest o...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
Pipe A alone can fill 75% of a cistern in 18 minutes. When both Pipe A and Pipe B are opened together, they can fill the entire cistern in 33 minutes. H...
- A contractor assigned 18 laborers to complete a task in 16 days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to ...
A man’s average income for the first 3 months is 12% of his total income. For the next 6 months the average monthly income was Rs. 25,400. His total i...