Priya, Riya, and Supriya can complete a piece of work
individually in (20/3) days, 20 days, and 25 days, respectively. If they work together, how many days will it take for them to complete 84% of the work? ÂSolution
Let total amount of work = 100 units (LCM of 20/3, 20 and 25) Efficiency of Priya = 100/(20/3) = 15 units per day Efficiency of Riya = 100/20 = 5 units per day Efficiency of Supriya = 100/25 = 4 units per day Amounts of work to be completed = 0.84 × 100 = 84 units Desired time = 84/(15 + 5 + 4) = 3.5 days
What does the legal maxim Qui Facit Per Alium Facit Per Se imply in the context of the law of agency?
Independence of Judiciary is inevitable in:
The consideration or object of an agreement is lawful, unless_______________
Under which section of CrPC Assistant Public Prosecutor is appointed by the state government?
Which of the following best represents the meaning of term ‘ultra vires’?
President makes an oath in the presence of …….
Which of the following is considered primary evidence under the Bharatiya Sakshya Adhiniyam, 2023?
Under the Information Technology Act, 2000, which section provides legal recognition to electronic records?
President’s rule is under which article of the constitution ?
Vested interest is :