Question

    A team of 'x' boys can complete a

    job in 18 days if they all work together. However, every day, 15 boys leave the team after starting the task, and it now takes 24 days to finish the work. Determine the value of '0.2x'.
    A 138 Correct Answer Incorrect Answer
    B 120 Correct Answer Incorrect Answer
    C 125 Correct Answer Incorrect Answer
    D 130 Correct Answer Incorrect Answer

    Solution

    ATQ, Let the efficiency of each boy be 'b' units/day. Total work = x × 18 × b = '18xb' units ATQ: 18xb = x × b + (x - 15 × 1) × b + (x - 15 × 2) × b + (x - 15 × 3) × b + .... + (x - 15 × 23) × b Or, 18x = 24x - 15 × (1 + 2 + 3 + .... + 23) Or, 6x = 15 × (23/2) × (23 + 1) [since, sum of first 'n' natural numbers = (n/2) × (n + 1) ] So, 'x' = 690 Therefore, required value = 0.2 × 690 = 138

    Practice Next