Question
Aman, Bhanu, and Chinu can complete a piece of work individually in 20 days, 30 days, and 60 days, respectively. How many days will Aman take to finish the work if Bhanu and Chinu assist him every third day?
More Quant Miscellaneous Questions
- The circle whose centre is (–3, 2) and which cuts off a chord of length 6 on the line 2x–5y+18=0 has radius:
- The average score of 10 students in a class is 85. After adding the scores of 5 new students, the average score becomes 90. What is the total score of the ...
- In an election between two candidates, winner got 40% of total valid votes. If total number of votes cast were 1700 out of which 10% were invalid, then fin...
- In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between x and y and choose the co...
- Arun invests Rs.(y – 2000) in a compound interest scheme at a rate of 12% per annum for 3 years. Rina invests Rs.y in a compound interest scheme at a rate ...
- Calculate the percentage increase in the total profit of all companies combined from 2020 to 2023.
- Person A can finish a task alone in 22(3/5) days, while Person B can complete the same task alone in 14(1/8) days. If A and B collaborate on the task, how ...
- The selling price of 8 shirts is the same as the cost price of 9 shirts. If each shirt is marked at 50% above its cost price, calculate the percentage disc...
- The pie chart below represents the degree distribution of employees across five different offices, with a total of 4500 employees in all five offices combi...
- What is the smaller angle between the hour hand and the minute hand of a clock at 3:25?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)