Question
A contractor was tasked with constructing a bridge
within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?Solution
Let the contractor employed ‘x’ more workers after 40 days. So according to question: (75 × 40)/0.75 = {(x + 75) × 5}/0.25 20x + 1500 = 4000 20x = 2500, x = 125 So, 125 more workers are required to complete the work on time.
Who among the following was the President of the Indian National Congress at the time of independence of India?
The average age of a group of 15 students is 20 years. Two persons of age 30 years and 44 years, left the group and 2 persons of age 25 years and 34 yea...
Some plants can also produce new plants from their roots. An example of such a plant is ______.
Which of the following statement is incorrect about “Pradhan Mantri Mudra Yojana”?
Consider the below statements and identify the correct answer.
Statement-I: If a substance loses oxygen during a reaction, it is said to be reduc...
Virat Kohli has played 122 innings and has an average score of 74 runs per inning. The difference between his highest and lowest scores in an innings is...
According to Factories act 1948, Every worker who has worked for at least ______ in a year is entitled to annual leave with wages.
Which one of the following is the correct chronological sequence of the given dynasties of Delhi Sultanate?
Which of the following pairs is incorrect?
What was the achievement of Dobereiner’s triads?