Question
A contractor was tasked with constructing a bridge
within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?Solution
Let the contractor employed βxβ more workers after 40 days. So according to question: (75 Γ 40)/0.75 = {(x + 75) Γ 5}/0.25 20x + 1500 = 4000 20x = 2500, x = 125 So, 125 more workers are required to complete the work on time.
Which Union Minister released the Assessment of Logistics Cost in India report in New Delhi?
Punyakoti Dattu Yojana is associated with?
Which of the following is the most widely used method for refining impure metals?
Who has been appointed as the Director General of the National Investigation Agency (NIA) as of 2024?
So far how many indigenous banks have got approval from the Reserve Bank of India (RBI) to open a special Vostro account for trade in rupees and both th...
E-commerce major Flipkart Group has committed to achieving a net-zero carbon emissions target in its own operations by ___.
For what pioneering endeavor did India secure the 9th GovTech Prize at the World Government Summit 2024?
- In which year was the export ban on broken rice imposed by the Indian government?
What is the success rate of direction control in the cyborg bee developed by China?
North India's first nuclear power plant will be set up in which state?