Start learning 50% faster. Sign in now
Let the total work be '60x' units. So, efficiency of 'A' = 60x ÷ 12 = '5x' units/day efficiency of 'B' = 60x ÷ 15 = '4x' units/day efficiency of 'C' = 60x ÷ 20 = '3x' units/day Work done by 'A', 'B' and 'C' together in 4 days = Work done by 'A' alone in 3 days + Work done by 'A', 'B' and 'C' together on 4th day Work done by 'A', 'B' and 'C' together in 4 days = 5x X 3 + (5x + 4x + 3x) X 1 = 15x + 12x = '27x' units So, Work done by 'A', 'B' and 'C' together in next 4 days = '27x' units Amount of work done in first 8 days = 27x X 2 = '54x' units Remaining work = 60x - 54x = '6x' units So, time taken by 'A' to complete the remaining work = 6x ÷ 5x = 1(1/5) days So, total time taken = 8 + 1(1/5) = 9(1/5) days
Select an appropriate figure from the four options that will come in the place of question mark (?) and complete the figure.
Which figure should replace the question mark (?) if the series were to continue?
In each of the following questions, find out which of the answer figures can be formed from the pieces given in the problem figure.
Select an appropriate figure from the four options that would complete the figure.