Question

    Time taken by A and B together to complete a work is 1

    day less than the time taken by B alone to complete the same work. With his half efficiency B can complete the work in 10 days. find the efficiency ratio of A to B.
    A 1:4 Correct Answer Incorrect Answer
    B 2:5 Correct Answer Incorrect Answer
    C 1:8 Correct Answer Incorrect Answer
    D 1:2 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    B's full efficiency: B completes the work in 5days (since with half efficiency, B takes 10days). A and B together: Time taken = 5−1 =4 days. Combined efficiency of A and B = 1/4 work units/day. B's efficiency = 1/5 work units/day. A's efficiency: Efficiency ratio (A:B): The efficiency ratio of A to B is 1:4 .