Question
Akash can finish a task alone in
24 days, while Akash and Bittu working together can complete the same task in 14 days. If Bittu starts the work alone and stops after 19.6 days, how many days will Akash need to finish the remaining work by himself?Solution
ATQ,
Let the total work = L.C.M of 24 and 14 = 168 units So, efficiency of ‘Akash’ alone = 168 ÷ 24 = 7 units/day Combined efficiency of ‘Akash’ and ‘B’ = 168 ÷ 14 = 12 units/day So, efficiency of ‘Bittu’ alone = 12 – 7 = 5 units/day Work completed by ‘Bittu’ alone in 19.6 days = 19.6 × 5 = 98 units Time taken by ‘Akash’ alone to complete the remaining work = (168 – 98) ÷ 7 = 10 day
In case of a defined benefit pension plan, the risk of investment and planning is with _____
Which of the following steps were taken during the Liberalisation process in India?
I- The new policy encouraged the entry of private sector firm...
Which rate has replaced LIBOR?
In cost accounting, overheads are classified into various categories based on the nature of the expenses. Which category do Director’s remuneration an...
Which of the following is not one of the major economic challenges that posed threat to global growth, according to the Economic Survey of 2023?
The air conditioners not working in the office is which of the following factors?
The Economic Survey 2023 projects a baseline GDP growth of ________ in real terms in FY24.
Recently RBI approved five banks to work with it on a pilot project for its digital currency -- the Digital Rupee, which of the following is not in the ...
What is the primary objective of the Corporate Debt Market Development Fund (CDMDF), as per SEBI Annual Report 2023-24? Â
What was the increase in the insurance density in India in FY24 as per economic survey 2023-24?