Question

    Pawan can finish a task in 28

    days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started working together but stopped after 10 days. Raja then completed the remaining work in 5 days. Determine how long Raja alone would take to complete the entire task.
    A 20 days Correct Answer Incorrect Answer
    B 18 days Correct Answer Incorrect Answer
    C 14 days Correct Answer Incorrect Answer
    D 22 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Time taken by 'Bhavna' to complete the work = 28 + 7 = 35 days Let the total work be 140 units (LCM of 28 and 35) Efficiency of 'Pawan' = (140/28) = 5 units/day Efficiency of 'Bhavna' = (140/35) = 4 units/day Work completed by 'Pawan' and 'Bhavna' in 10 days = (5 + 4) × 10 = 90 units Remaining work = 140 - 90 = 50 units So, efficiency of 'Raja' = 50/5 = 10 units/day Therefore, time taken by 'C' to complete the entire work = 140/10 = 14 days