Question
Pawan can finish a task in 28
days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started working together but stopped after 10 days. Raja then completed the remaining work in 5 days. Determine how long Raja alone would take to complete the entire task.Solution
ATQ,
Time taken by 'Bhavna' to complete the work = 28 + 7 = 35 days Let the total work be 140 units (LCM of 28 and 35) Efficiency of 'Pawan' = (140/28) = 5 units/day Efficiency of 'Bhavna' = (140/35) = 4 units/day Work completed by 'Pawan' and 'Bhavna' in 10 days = (5 + 4) × 10 = 90 units Remaining work = 140 - 90 = 50 units So, efficiency of 'Raja' = 50/5 = 10 units/day Therefore, time taken by 'C' to complete the entire work = 140/10 = 14 days
If the beta of the market index is 1 and the standard deviation of the market index increases from 12% to 18%, what is the new beta of the market index?
Which of the following is a result of a well-functioning financial market?
Which of the following is not a feature of debentures?
What growth forecast for India did S&P Global Ratings retain for FY25?
Which of the following Documents is required to open and maintain Retail Direct Gilt Account’ (RDG Account) with RBI.
Which of the following is not a type of liquidity risk?
What initiative was launched by SIDBI in 2018 to track the current state and expected outlook on the MSME sector?
Which of the following is a type of life insurance policy that combines insurance coverage with investment?
1)Term life insurance
2)Whole ...
An organizational structure that is characterized by democratic and inclusive styles of management can be described as ?
Which of the following is typically excluded from the calculation of the firm’s working capital needs when using the Operating Cycle method?