Question
A and B can complete a piece of work in 12 days and 15
days respectively. They start working together, but after 4 days, A leaves. In how many more days will B complete the remaining work?Solution
Work done by A and B in 1 day = (1/12 + 1/15) = 5/60 + 4/60 = 9/60 = 3/20. Work completed by A and B together in 4 days = 4 * (3/20) = 12/20 = 3/5. Remaining work = 1 - 3/5 = 2/5. Work done by B in 1 day = 1/15. Time taken by B to complete 2/5 of the work = (2/5) ÷ (1/15) = (2/5) * 15 = 6 days. Correct Option: a
Anthracnose in guava is caused by which pathogen?
Which crop is related to "Durgapura Madhu" variety ?
Which fruit is most suitable for Jelly making ?
Lycopene development in tomato is adversely affected when temperature goes beyond ___
Which of the following substance of opium is used in Cough Syrups?
Pusa Himani, Pusa Safed and Arka Nishant are the varieties of _____
Which fruit have highest in vitamin-C is ?
Which of the following system of training of grapes has highcost benefit ratio
Most commonly used Oxygen absorbers used in Modified Atmospheric Storage structure is:
Which plant growth regulator is commercially used in grapes for berry elongation?