Question
A and B together can complete a work in 12 days, and B
alone can complete it in 20 days. How many days will A take to complete the work alone?Solution
Work done by A and B in one day = 1/12. Work done by B alone in one day = 1/20. Work done by A alone in one day = 1/12 - 1/20 = (5 - 3) / 60 = 2/60 = 1/30. A will take 30 days to complete the work alone. Correct Option: c
To digitise the insurance marketplace to the benefit of policyholders, the Insurance Regulatory and Development Authority of India (IRDAI) has launched ...
The ratio of a firm’s property, plant, and equipment, net of accumulated depreciation, to its annual depreciation expense is an estimate of:
What is the name of Indian Overseas Bank’s (IOB) credit scheme dedicated to organic farming?
What is the new LTV ratio for gold loans up to ₹2.5 lakh after RBI’s revision?   Â
RIDF is recently in news, Identify the “I” ?
Options, which do not have offsetting positions, are calledÂ
What is the maximum equity allocation allowed under the Active Choice in NPS? Â
 DuPont analysis is:
SEBI had mandated the separation of the posts of Chairperson and MD of listed companies by April 01, 2022. This norm was a part of recommendations of t...
What percentage did Indian startup funding decrease by in 2023 compared to 2022, according to data from Tracxn?