Question
A group of 8 men or 10 women can complete a certain
task in 21 days. How many days will it take for a combination of 10 women and 4 men to complete the same task?Solution
It is given, 8 men = 10 women (based on their efficiency) 10 women + 4 men = 10 women + 4 × (10/8) women = (10 + 5) women = 15 women So, w1 × t1 = w2 × t2 10 × 21 = 15 × t2 t2 = 14 days.
Number of male employees in HR and Production departments together were how much more than the number of female employees in IT department?
Find the ratio of number of Green apples sold by ‘P’ and ‘S’ respectively.
Calculate the total revenue generated from each clothing item over the six-month period. Based on this data, determine the overall profit or loss for th...
Find the total Cost Price of masks for all the companies together.
Find the number of females of tribe Dimasa.
Total Interest Earned by Bhavya:
If the boutique introduces a new product line of Accessories with a cost price of ₹400 and a selling price of ₹600, and they sell 200 units in the n...
Assuming that the boutique plans to increase the price of Casual Wear by 10% next quarter, and If the same quantity of 600 units is sold at this new pri...
Find the average number of Butter cookies baked on Monday, Tuesday and Wednesday together.
What is ratio between total numbers of employees who are unmarried to total number of female employees who are married?