Question

    4 girls working together for 1

    day complete the same amount of work as 6 men working together for 1 day. The efficiency of 1 man is 50% of the efficiency of 1 girl. Additionally, 1 boy, 1 girl, and 1 man together can finish the project in 5 days. How many days will it take for 1 boy to complete the project alone?
    A 22 days Correct Answer Incorrect Answer
    B 18 days Correct Answer Incorrect Answer
    C 12 days Correct Answer Incorrect Answer
    D 10 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Since, work done by 4 boy together in 1 day is equal to that done by 6 girls together in 1 day. 4x = 6y 2x = 3y --------(1) Since the ratio of efficiency of one men is 50% of that of one girl. 1y = 2b --------(2) From equations (1) and (2): 2x = 3y = 6b The ratio of time taken by 1 boy, 1 girl and 1 men alone to complete work: 2: 3: 6 Let the time taken by 1 boy, 1 girl and 1 men alone to complete the work be ‘2p’, ‘3p’ and ‘6p’ days respectively. So, (1/2p) + (1/3p) + (1/6p) = 1/5 p = 5 Time taken by 1 boy alone to complete the work = 2 × 5 = 10 days

    Practice Next

    Relevant for Exams: