Question

    Pawan, Bittu, and Raju can individually complete a task

    in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops after 5 days. Additionally, Pawan leaves the work 18 days before its completion. How many days does it take to complete the entire task?
    A 30 days Correct Answer Incorrect Answer
    B 18 days Correct Answer Incorrect Answer
    C 28 days Correct Answer Incorrect Answer
    D 42 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let the total work = 180 units (LCM of 36, 60 and 30) Amount of work done by Pawan alone in one day = 180/36 = 5 units Amount of work done by Bittu alone in one day = 180/60 = 3 units Amount of work done by Raju alone in one day = 180/30 = 6 units Amount of work done by Pawan, Bittu and Raju together in 5 days = 5 × (5 + 3 + 6) = 70 units Amount of work done by Bittu alone in 18 days = 18 × 3 = 54 units Remaining work = 180 – 70 – 54 = 56 units Time taken by Pawan and Bittu together to complete 56 units work = 56/(5 + 3) = 7 days So the total time taken to complete the work = 5 + 18 + 7 = 30 days 

    Practice Next