Question
Aman can complete a task in 12 days, while Bhanu alone
can complete the same task in 18 days. Aman starts the work alone and continues for 4 days. Then, Bhanu joins him, and they work together for the next 3 days. After that, Aman leaves, and Bhanu completes the remaining work alone. Determine how many days Bhanu worked alone to finish the task.Solution
ATQ; Let the total task be = 36 {LCM(18, 12)} Efficiency of ‘Aman’ = (36/12) = 3 units/day Efficiency of ‘Bhanu’ = (36/18) = 2 units/day task done by ‘Aman’ in 4 days = 3 × 4 = 12 units task done by ‘Aman’ and ‘Bhanu’ together in 3 days = 5 × 3 = 15 units Remaining task = 36 – 12 – 15 = 9 units Time taken by ‘Bhanu’ to complete the remaining task = 9/2 = 4.5 days
The number of students passed in college A is what percent (approximately) the number of student passed in college C? (During all the given year)
Find the ratio between the number of children visiting Buxa Tiger Reserve and Betla National Park together.
What is the average number of women visiting all the Parks together?
The total number of children visiting Kanha National Park is approximately what percent of number of children visiting Indravati National Park?
What was the ratio of the total number of students passed and failed in college C (during all the given years?

If the number of cars produced by Company P increased by 20% in 2023 compared to 2022, how many cars would be produced by Company P in 2023?
In 2021, what is the difference between the number of cars exported by Company P and Company R ?
What is the difference between the total number of orders who were not delivered by Jabong and Myntra together and that of who were not delivered by Fl...
What is the approximate average number of students failed in college C in during all the given year?