Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
In which type of flower does the margin of the thalamus grow upward and enclose the ovary completely, making the ovary inferior?
Which Indian state leads in cotton production?
The term pulsing is related to-
Bhata (entisols) of Chhattisgarh belongs to which textural group or texture?
Information about changes in forest covers and land use is essential to understand their contribution to the emission or reduction of greenhouse gases a...
The synthesis of ATP via electron flow through the ETS, with oxygen as the terminal electron acceptor, is known...
The relationship between the crop yield and weed competition is:
What is the Minimum Support Prices (MSP) for Cotton (long Staple) for Marketing Season 2024-25?
Iron in milk is
According to RBI rules how much loan can be given to poor and small farmers?