ATQ,
Fraction of work completed by 'Ramesh' = (24/40) = (3/5)
Remaining work = 1 - (3/5) = (2/5)
Time taken by 'Suresh' to complete (2/5)th of the work = 30 days
Time taken by 'Suresh' to complete the whole work = 30 × (5/2) = 75 days
Therefore, time taken by 'Suresh' to complete 75% of the work = 0.75 × 75 = 56.25 days
A person spent 12.5% of his monthly income on food and 32% of the remaining on rent. If amount spent on rent is Rs 1512, then find the amount spe...
Ravi allocated 60% of his income to expenses in May. In June, his savings increased by 20%, amounting to Rs. 5760. Calculate Ravi's total income for the...
A spent 30% and 26% of his monthly salary on food and rent, respectively. Of the remaining amount, he gave 20% and 40% to his mother and brother, respec...
In 2020, a city had 'q' trees planted along the streets. The number of trees increased by 40% in 2021 and another 35% in 2022. The number of trees decre...
A factory produces 800 units of product A in 5 days. If the production rate increases by 25% after 3 days, how many days will it take to produce a total...
There are 100 students in a particular class. 60% students play cricket, 25 % play football and 15% play both the games. What is the number of students ...
Virat allocates his income as follows: he spends 35% on rent and 25% on groceries. From the amount he has left, he donates 25% and saves the remainder. ...
Suresh’s monthly salary is equal to 30% of Mahesh’s monthly salary. Mahesh’s monthly salary is Rs. 28000 less than Mohit’s monthly salary. If M...
A gave 40% of amount to B. B gave 30% of amount received from A to C. If amount received by C from B is Rs.144, then find the amount received by B from A.