Question
The efficiency of P, Q, R, S are in the ratio of
6:5:4:3. If P and R can do a work together in 6 days. Then How many days Q and S will take to complete the same work?Solution
Efficiency of (P+R) = (6+4) = 10 Days taken by (P + R) together to complete the work = 6 days Efficiency of (Q + S) = (5+3) = 8 So, Q and S will take time = (Total days of (P + R) × Total Efficiency of (P + R)) / (Total Efficiency of (Q + S)) = (6 ×10)/8 = 60/8 = 7(1/2) days
Under the Sub-Mission on Agricultural Mechanization (SMAM), what is the maximum financial assistance provided for the purchase of drones for demonstrati...
Which identification method has been newly approved for livestock insurance?
When variable cost is zero, the total cost will be?
I. Equal to variable cost
II. Equal to fixed cost
III. Equal to average variable cost
Under the revised PMFBY framework, Wild Animal Attack has been added as which type of cover?
Growth regulator used in hybrid rice seed production programme is
(a) NAA
(b) GA
(c) CCC
(d) ABA
Loose smut in wheat can be effectively controlled by
Evaporative cooling system works on main principle of
Recovery phase or transplanting shock of transplanted rice is around _________ from the date of transplanting:
India ranks ______ globally in milk production as per the latest data in BAHS 2024?
Satellite-based crop yield estimation under PMFBY is carried out using which system?