Question
P can complete a piece of work in 15 days. Q in 20 days
and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how many days, altogether, was the work completed (in days)?Solution
Work done by ( P + R ) in 3 days = 3(1/15+1/30) = 3((2+1)/30)=3/10 Remaining work = 1-3/10=7/10 ( Q + R )’s 1 day’s work = 1/20+1/30 = (3+2)/60 = 5/60 = 1/12 Time taken by ( Q + R ) to finish 7/10 part of the work = 12 × (7/10) = 42/5 days = 8(2/5) days Total time = 3 + 8  = 11`2/5`  days. Alternate Method:    P      Q      R   15     20      30 LCM = 60 units Eff 4  :   3  :   2 (P+R)'s 3 days work = (4+2)×3 = 18 units So remaining is done by P & R in = (60-18)/(3+2) = 42/5 days So total days = 3 + (42/5) = 57/5 days
148, ‘?’ , 15 4 , 17 8 , 23 8 , 35 8 , 56 8
3601 3602 1803 604 154 36
...8, 7, 12, 35, 128, 635
14, 28, 54, 98, 154, 224
104Â Â Â Â Â 136Â Â Â Â Â 152Â Â Â Â 160Â Â Â Â Â 164Â Â Â Â Â ?
...A’ is the nth term of the given series and ‘B’ is the (n + 1)th term of the given
series. Choose the correct statement from the following s...
7    7       14    42   ?     840
...11Â Â Â 12.1Â Â Â Â 14.3Â Â Â Â 17.6Â Â Â Â Â 22Â Â Â Â Â ?
9Â Â Â 4.5Â Â Â 4.5Â Â Â 9Â Â Â 36Â Â Â ?
40 30 20 ? 7.5 4.375