Question
A group of workers was put on a job. From the second day onwards, 1 worker left work everyday. If no worker was left when 52% of the work gets completed, find the number of workers in the group initially?
More Time and work Questions
- Team A can built a project in 4 hours less than the time taken by Team B to built the same project. The ratio of the strength of Team A to that of Team B ...
- 'A' and 'B' alone can complete a work in 14 days and 21 days, respectively. Find the time taken by them to complete the work if they work on alternate days...
- The efficiency ratio of D, E, and F is 1:2:5. Together, they complete a project in 16 days. If D and E contribute for 14 days and leave, how long will F ta...
- A can complete a work in 20 days. B takes 10 days less than A to complete the same work. In how many days can both of them together complete 90% of the wor...
- There is enough food in a camp to last for 40 days if each of the 60 soldiers present at the camp eat 3 times a day. After 10 days, 10 soldiers left the ca...
- 'A' alone can finish a job in 12 days. If 'A' is twice as efficient as 'B' who is 20% as efficient as 'C', then find the time taken to finish the job if th...
- X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the valu...
- P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P...
- Number of days taken by ‘P’, ‘Q’ and ‘R’ to do a certain work alone is (x + 4) days, (x - 11) days and (x - 1) days, respectively and number of days taken ...
- Suppose ‘n’ employees can process all the files in 50 days. If 10 more employees had participated, the work would be completed in 30 days. Find the value o...