Question
3 men dig a hole in 10 days. How many days would it take for 5 men to dig the same hole ?
More Time Questions
- In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- A trip from Mumbai to Pune takes 4 hours 30 minutes at a speed of 60 km/hr. How long (in hours) will it take to complete, if the speed is 15m/sec?
- What % of a day is 30 minutes ?
- Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
- A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working t...
- Working alone, B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working toget...
- X, Y and Z together can complete a work in 15 days. X and Y together can complete the same work in 30 days. Z alone can finish the same work in how many da...
- A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left....
- A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone he can do th...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)