3 men dig a hole in 10 days. How many days would it take for 5 men to dig the same hole ?
More Time Questions
- P and Q can complete a project in 15 days and 10 days, respectively. They started doing the work together, but after 2 days, Q had to leave and P alone com...
- A contractor hires 12 workers to complete a project in 20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How...
- 'K' can do 3/4th of a work in 6 days and 'J' can do 2/5th of the same work in 4 days. How long (in days) will they take, if they work together to finish th...
- A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work....
- A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12.5% ...
- A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 12 days, and C alone in 24 days, in what t...
- A man on the top of a tower, standing on the sea-shore, finds that a boat coming towards him takes 10 minutes for the angle of depression to change from 30...
- A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone w...
- Harish and Bimal can complete a task in 20 days. They worked at it for 15 days and then Bimal left. The remaining work was done by Harish alone, in 10 days...
- A and B can complete a work in 40 and 60 days respectively. They started a work which is to be completed in 20 days. But it was found that they are lagging...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt