A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work, is:
Let the total work be 120 units. (LCM of 24, 15 and 12 is 120.) Efficiency of A = work/time = 120/24 = 5 units/day Efficiency of B = 120/15 = 8 units/day Efficiency of C = 120/12 = 10 units/day Work done by B and C in 3 days = (8 + 10) 3 = 54 units Remaining work = 120 - 54 = 66 units Time taken by A to complete the remaining work = 66/5 = 13(1/5)
If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days how many men are required to dig additional 4 meter of the tunnel (of the same...
3 men dig a hole in 10 days. How many days would it take for 5 men to dig the same hole ?
X, Y and Z together can complete a work in 15 days. X and Y together can complete the same work in 30 days. Z alone can finish the same work in how man...
Two cars start from a house at an interval of 10 minutes and travel at a speed of 20 km/hr. With how much speed (km/hr.) should a woman coming from the ...
A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
A and B can complete a piece of work in 120 days, B and C can complete it in 150 days, and A and C can complete it in 200 days. In how many days can B ...
A and B can finish a work working on alternate days in 19 days, when A works on the 1st day. Similarly, they can finish the work working on alternate da...
A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and le...
Pipe A can fill the tank 5 times faster than pipe B, if pipe A and B together fill the tank in 50 minutes, then pipe B alone can fill the tank in:
Three pipes, A, B, C can fill an empty cistern in 2, 3 and 6 hours respectively. They are opened together. After what time should B be closed, so that ...