A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
Let efficiency of B be 4 units/day Efficiency of A = 4 × (7/4) = 7 units/day We know, Total work = Efficiency × Time taken Total work = (7 + 4) × 21 = 231 units 100/3 % of the total work = 231 × 100/300 = 77 units A alone can complete 100/3 % of the work in = 77/7 = 11 days
Many politicians in the past have won elections by promising to cut taxes, most of the new ones now ……………………….
...Colleges cannot ______ to ragging because of the Anti Ragging Act.
Dead Ringer
Economists argue about a lot of things, yet many would probably see eye to eye on the benefits of free trade, which generates wealth by allow...
The difficulty is trying to spot something big before it becomes a problem but not crying bee too often.
Select the most appropriate meaning of the given idiom.
Raise the bar
to back the wrong horse
Angry residents are up in arms over a proposal to site a giant mobile phone mast near their homes.
Up against the wall
In each question below, a sentence is given with an idiom/phrase printed in bold type. That part may contain a grammatical error. Each sentence is follo...