Question
15 male employees or 20 female employees of a company
can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?Solution
15 males × 26 days = 20 females × 26 days ∵ 15 males = 20 females ∴ 30 males = 40 females Total work in terms of females = 20 females × 26 days = 520 units No of days taken by 30 males and 12 females: ⇒ (40 females + 12 females) = 52 females ∴ No of days taken = 520 units /52 females = 10 days
Who can become a partner in a Limited Liability Partnership?
A small company is a company whose paid-up capital and turn over shall________________
In case of a female defendant after her marriage_______________.
The appropriate Government may, by notification in the Official Gazette, appoint such persons as it thinks fit to be ______________ for the purposes of ...
A person who receives a negotiable instrument in good faith for valuable consideration is known as
Among the following which section deals with the admissibility of Evidence shall be decided by the Judge_____
Under the Patents Act, 1970, what is the term of a patent granted in India from the date of filing?
Who shall constitute the Cyber Regulations Advisory Committee under section 88 of the Information Technology Act, 2000?Â
Which of the following statement in respect of section 320 of the Code of Criminal Procedure, 1973, is not correct?
As per Art. 213 of the Constitution, once an ordinance has been promulgated by the Governor in a State it will cease to operate within _________ from r...