Question
15 male employees or 20 female employees of a company
can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?Solution
15 males × 26 days = 20 females × 26 days āµ 15 males = 20 females ∴ 30 males = 40 females Total work in terms of females = 20 females × 26 days = 520 units No of days taken by 30 males and 12 females: ⇒ (40 females + 12 females) = 52 females ∴ No of days taken = 520 units /52 females = 10 days
According to the RBIās January 2024 circular, banks must implement a specific reporting framework for unclaimed deposits. Which of the following best...
As per realization principle, revenue will be recognized:
The term āfinancial creditorā in the Insolvency and Bankruptcy Code (IBC) in India means?
Which of the following financial ratios is most critical for assessing the creditworthiness of an MSME for working capital financing?
Total sales Rs. 20,00,000; Fixed expenses Rs. 4,00,000; P/V Ratio 40%; Break-even capacity in percentage is__________.
Which of the following risk can reduce the value of a bond or other fixed rate investments?
Who introduced the concept of 'Accredited Investors' in the Indian securities markets?
Which of the following is a potential benefit of investing in REITs?
Which of the following does not contribute to early identification of stressed assets?
Which of the following types of documentary credit allows the beneficiary (exporter) to receive payment even if the documents do not comply with the exa...