Question

    If 10 men can complete a piece of work in 12 days by

    working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?
    A 16 Correct Answer Incorrect Answer
    B 15 Correct Answer Incorrect Answer
    C 10 Correct Answer Incorrect Answer
    D 12 Correct Answer Incorrect Answer

    Solution

    The correct answer is C