A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B work to finish the work completely?
Total work = 48 (LCM of 16 and 12) Efficiency = Work/Time Total efficiency = 3 + 4 = 7 units Remaining work after 4 days = 48 - (7 × 4) = 48 - 28 = 20 units Time is taken by B to finish the remaining work = 20/4 = 5 days Total number of days B work = 4 + 5 = 9 days ∴ B work the total number 9 days to finish the work completely.
Where is the Headquarter of Asian Development Bank?
...Under which article of Indian Constitution the Finance Commission is constitued?
Ustad Amjad Ali Khan is famous for playing which musical instrument?
Who founded the city of Amritsar?
The first phase of bank nationalization began in the year of
Prathama Bank was sponsored by SBI
Who had composed the Geeta Govinda or Gita Govinda?
The Capital of Sierra Leone is
Greenland Island is in which ocean?
Which of the Following Day is not observed in January?