Question
A and B can complete a work in 40 and 60 days
respectively. They started a work which is to be completed in 20 days. But it was found that they are lagging behind the schedule, so a third person C was appointed after 12 days to complete the work on time. In how many days C can alone complete the work?Solution
A and B worked for 20 days. In 1 days, they could have completed work (1/40 + 1/60) = 1/24 So, in 20 days, they did (1/24) *20 = 5/6 This means C did 1 – 5/6 = 1/6 of work in 8 days So, he can do work alone in 48 days.
How does the maximum tenor of takeout finance provided by IIFCL relate to the economic life of the project, expressed as a percentage?
As per RBI draft prudential guidelines for Advances - Projects Under Implementation, Directions, 2024, the original or revised repayment tenor, includin...
In case of an infrastructure project, a project finance accountĀ classified as āstandardā shall continue to be classified as āstandardā on acco...
The Reserve Bank of India (RBI) has issued a framework for recognizing Self-Regulatory Organizations (SROs) in the financial technology sector (SRO-FT)...
Calculate the asset turnover from the above information.Ā
The Central KYC Record registry in India is ____________? Ā
Within one year of incorporation, what should be the ratio of net owned funds to the depositsĀ for Nidhi companies?
Under the regulation of which act can scheduled commercial bank take equity stake in a payments bank to the extent permitted?
What would be the break even units if the Fixed Cost is Rs.1,00,000 and PV ratio is 25%. The company sells its product at Rs.60 per unit.
Which of the following is a contingent credit line sanctioned for the project at the time of financial closure to fund any cost overrun during the con...